|
Power sector
reforms: can we overcome the crisis?
By Usama
Siddiqui
Pakistan has faced perennial load-shedding and
frequent power outages over the past three decades, a problem which has
most recently caused serious civil unrest and disturbances. A high demand
growth rate has seen supply lag far behind. The state utilities suffer
immensely from non-payment of dues, transmission losses, underinvestment,
circular debt crisis, and general inefficiencies of manpower and plants.
Since independence in 1947, Pakistan had been
primarily dependent for its electricity needs on the two state-owned
vertically integrated power monopolies, Water and Power Development
Authority (Wapda) and Karachi Electric Supply Company (KESC). While KESC
covered the large demand centre of the business city of Karachi, Wapda
covered the rest of the country. Both were fully-integrated generation,
transmission and distribution companies and controlled by the government
through the ministry of water and power.
Out of Pakistan’s net effective generation capacity
of 19,000MW, as of end ’10, Wapda and KESC contributed 61 per cent.
Independent Power Plants (IPPs) and nuclear make up the rest (see figure
1). However, Wapda’s hydel plants lose almost 3,000MW in the winters
when the water reservoir levels drop dramatically due to lesser rainfall.
Evolution of power demand and supply
In the late 80s and early 90s, Pakistan’s total
installed capacity hovered around 10,800MW. A burgeoning population
coupled with robust economic growth reflected by an average GDP annual
growth rate of 7 per cent in the 80s (see Figure 2) brought about a sharp
increase in overall electricity demand.
It proved to be a severe strain on the existing power
capacity with an estimated 2,000MW peak load shortfall. Electricity was
effectively available to only 40 per cent of the population.
To tackle the chronic power shortages, the PPP
government attracted several IPPs under its friendly 1994 Power Policy.
While the manner of some contract awards and the costly tariff regime were
much criticised, the 1994 policy did manage to add a total installed
capacity of 6,000MW to the grid through 16 new IPPs from ’97 to ’01.
Unfortunately, the Asian financial crisis of the late
90s and the ’98 nuclear tests had a detrimental effect on Pakistan’s
economy. As a result, demand for electricity slumped and Pakistan was
faced with expensive IPP electricity, that were guaranteed capacity
payments despite their under utilisation.
Post the 9/11 New York attacks, Pakistan benefited
from the increased remittances (averaging $4 billion p.a.) sent back by
expatriates as well as the inflows from western allies in the war on
terror. This coupled with the military-led governments steady economic
reforms resulted in Pakistan’s real GDP growing at a robust 7 per cent
p.a. from ’04-’07. This had a direct bearing on the country’s
electricity consumption which registered a phenomenal average annual
growth rate of over 10 per cent during the same period.
The surplus capacity generated by the IPPs’ in the
late 90s had however made the military government complacent and it only
woke up to upcoming demand-supply gap in ’07. A new wave of IPP projects
was signed that will add 2,632MW from ’09 to ’11. The controversial
Rental Power Plants (RPPs) would also add to capacity. The recent and
forecast demand-supply trend of Pakistan is highlighted in figure 2.
Sectoral reforms and liberalisation
Since their inception, both Wapda and KESC had been
plagued with inefficiencies, poor governance, red-tape, and political
interferences. Transmission & Distribution (T&D) losses amounted
to 30-40 per cent.
This was as much a result of a lack of adequate
investment in the strained transmission network as of the power thefts by
various groups and individuals. On average, about 20 per cent of dues were
not recovered, most of them owed by other public sector entities.
As a result of these inefficiencies, successive
governments injected significant subsidies into them to keep the end
consumer tariff manageable so as to minimise political damage. To counter
these chronic problems and encouraged by the donor agencies like World
Bank and Asian Development Bank, the government embarked on an ambitious
power-sector restructuring and liberalisation programme in the 90s, with
an eventual aim of privatising the loss-making entities and moving towards
a market-driven electricity sector.
In 1997, the National Electric Power Regulatory
Authority (NEPRA) was established to grant licenses, monitor standards and
practices, enforce competition, and safeguard the interest of the consumer
by determining tariffs.
Wapda’s corporatisation and unbundling
In 1998, Pakistan Electric Power Company (Pepco) was
created to manage the unbundling of Wapda’s assets. Hydel power
generation continue to be managed under the banner of Wapda, which
retained ownership of the 14 hydel plants. The thermal plants were
distributed into 3 Generation Companies (Gencos), according the geographic
location of the plants. The Gencos and Wapda hydroelectric sell their
electricity to the National Transmission and Dispatch Company (NTDC),
which acts as a single buyer and is responsible for the entire
transmission network. This electricity is transmitted downstream to 8
Distribution Companies (Discos), for onward distribution and billing of
end consumers covering their respective geographic regions. The power
produced by the IPPs under their PPAs also flows through this Pepco
system.
The restructuring of Wapda led by Pepco has hardly
been a success. While the individual entities were created, they have yet
to become independent and fully autonomous. Pepco still exercises
influence over the financial transactions and governance issues of the
Discos and Gencos, and monitors the sale and purchase of power up and down
the value chain.
From ’03 to ’07, despite NEPRA having notified
significant increases in tariffs in view of the rising fuel costs, the
government kept the consumer tariff frozen due to political reasons,
choosing instead to give subsidies. However, the ballooning international
fuel prices meant the government could not service its subsidies in time.
The Discos incurred huge losses as they could not pass on the cost of
electricity purchased to the end customer and defaulted on their payment
obligations to the Gencos, Wapda and IPPs. The Gencos and IPPs then
defaulted on their payments to the fuel suppliers (PSO, Shell, SSGC, SNGPL),
who in turn have defaulted on their payment obligations to refineries,
E&P companies, and international fuel suppliers. An alarming
‘circular debt crisis’ has emerged, that in May 2010 stood at Rs500
billion.
Other factors hampering the profitability of the
Discos include their continued inability to recover dues especially from
the public sector and provincial governmental departments, a legacy
bureaucratic mindset in governance, and high losses in the distribution
systems. Gencos are running on average at only 67-90 per cent of their net
available capacities due to not having conducted maintenance and scheduled
outages over the years as per standard industry practices. Finally, the
required contracts between Gencos and NTDC, NTDC and Discos, and Gencos
and Discos are still not in place.
The then government initiated efforts to privatise
KESC in ’96. The management was brought under army control to recover
the T&D losses. The government assisted financially in cleaning up its
books and wiped out its accumulated losses. In ‘05, the fully integrated
utility was finally sold to a Saudi group who later sold their stakes in
’08 to Middle East’s private equity giant, Abraaj Capital.
The privatisation has been a mixed story at best.
T&D losses have averaged 35 per cent since privatisation, only
marginally down from the 40 per cent prior to that. New generation
capacity additions are not due before 2012. The streets of Karachi over
the last two years have become a battleground against the frequent
loadshedding that has continued unabated. The new management has had
troubles with the powerful labour unions in attempting to initiate new
human resource reforms and rationalisation of the workforce. KESC has at
times not produced at peak capacity, to avoid purchasing expensive furnace
oil, preferring instead to purchase cheaper electricity from the Pepco/NTDC
system. This is clearly a downside of privatising monopolies as fully
integrated entities and in an environment where the market is not
competitively structured. Finally, KESC too is involved in the circular
debt crisis owing large payments to Pepco and its fuel suppliers.
Despite still making losses, the new management should
however be credited for lobbying hard to get tariffs reflective of market
realities and for clamping down on the rampant culture of power theft in
Karachi. Also, efforts to increase the older plants’ capacity are
beginning to bear some fruit. Government planners and donor advisors
should keep in mind that Pakistan is still far from being a fully
liberalised and competitive market. A new experiment in liberalisation
needs to be carefully managed and implemented, with the commercial
capacity and regulatory framework well in place before embarking on it.
The deregulation, liberalisation, and unbundling of
the sector should gather more momentum so that all players can compete on
an equal footing. If all market players compete fairly, the end objective
of the cheapest prices for the end customer should be achievable. The
ongoing move towards a market-oriented system would encourage not just
KESC/ex-Wapda entities but also private players like the IPPs to maximise
efficiencies in order to retain their consumers.
|