|
Germany Funded
Projects
What has become of the talks for
funding eight hydropower projects?
It’s nearly five years since the talks were initiated, but
nothing concrete seems to have come out of them to date
By Kaleem Omar
T.S. Eliot said, “Between the reality and
the response / falls the shadow.” This is true of many things,
including, in Pakistan, the whole issue of economic problems. The
“reality”, in this context, is the specific problem that needs to be
addressed. The ‘response” is what, if anything, is done about it. The
‘shadow” is the time lag between the identification of a project and
its implementation. This time lag often tends to stretch and stretch for
so many years that the project in question either ends up costing many
times the original estimate or is abandoned altogether.
One of the main reasons for this unfortunate state of
affairs is an inefficient implementation methodology and the lack of a
monitoring mechanism that would keep the government of the day informed
about the project’s rate of progress and hindrances standing in the way
of speeding things up.
A case in point is the talks that were initiated with
Germany back in January 2001 to arrange funding for the construction of
eight hydropower projects.
A two-member delegation from Germany’s KFW bank, a
state-owned export finance agency, arrived in Islamabad on January 19,
2004 for three days of talks with Pakistani officials on funding eight
hydropower projects. The delegation, consisted of KFW’s Asia Division
Energy Sector Policy Chief Peter Pischke and Policy Project Manager Olaf
Zymelka, also discussed the funding of several power distribution projects
with Wapda’s National Transmission Dispatch Company, including the 550kv
Ghakhar Mandi Grid Station Project.
The high-head hydropower generation projects included
the 963mw Neelum-Jhelum Hydropower Project, the 130mvv Duber Khwar
Hydropower Project and the 28mw Summer Garh Hydropower Project. The
low-head hydropower generation projects included the 120mw Taunsa
Hydropower Project, the 16mw Rohri Canal Hydropower Project, the 9.66mw
Upper Chenab-M Hydropower Project, the 5.83mw Upper Chenab-L Hydropower
Project, the 1.5mw Chor Nullah Hydropower Project and the 1.25mw Spath Gah
Hydropower Project.
The original plan of the Neelum-Jhelum Hydropower
Project envisaged the diversion of the waters of the River Neelum waters
at Nauseri, about 41 km upstream of the Domel bend, through tunnels to
create a head of 213 metres out-falling near Majhoi into the upper limb of
the River Jhelum, for generating 500mw of power.
However, under an agreed improved option presented by
the project’s Norwegian consultants, Norconsult International, the plan
later called for the waters of the River Neelum to be diverted into the
lower limb of the River Jhelum in a single stretch through a 32.5 km-long
tunnel system, thereby generating 963mw of power.
Norconsult began work on updating the project’s
feasibility report in January 1995 and completed the project’s detailed
engineering design in 1997, under a credit arrangement signed with the
Norwegian government.
The project was offered to the Private Power Cell of
the Azad Kashmir government through the Ministry of Water and Power’s
Private Power Infrastructure Board for bidding under the Pakistan
government’s 1998 power policy, which that year replaced the Benazir
Bhutto government’s 1994 power policy.
Meanwhile, preliminary work on the project continued
under the auspices of the Water and Power Development Authority’s
Hydro-Electric Planning Organisation, with the approval of the Ministry of
Water and Power. The revised PC-1 was prepared and submitted to the
ministry for approval in January 1999. But approval was not granted at
that time due to the expected implementation of the project in the private
sector.
The Pakistan government later decided to implement the
project in the public sector, with Wapda being designated as the
implementing agency. The project’s updated and revised PC-1 was
eventually approved by the Executive Committee of the National Economic
Council (Ecnec) in February 2002, for a total cost of Rs 84.50 billion,
including a foreign exchange component equivalent to Rs 46.66 billion.
Documents to pre-qualify bidders for the project were
vetted by Wapda’s Central Contract Cell in 2003. Expressions of Interest
from construction companies for building the project were expected to be
invited by Wapda as soon as arrangements for financing the project had
been firmed up with foreign aid donors.
It was in this context that the January 2004 talks in
Islamabad with the KFW delegation took place, following up on talks held a
few days earlier in Bonn. At the Bonn talks it was decided that Germany
would send a KFW team to Pakistan to inspect the Neelum-Jhelum project
site as well as other hydropower projects sites and hold talks with
Pakistani officials on financing the projects. The KFW team arrived in
Pakistan on January 19, 2004 and was expected to visit the project sites
that same week.
KFW has been involved in financing public sector
projects in Pakistan for many years. The projects include many in the
power sector.
The 130mw Duber Khwar Hydro Power Project was to be
built on the River Duber Khwar, a right-bank tributary of the River Indus
near Pattan in NWF, 265km from Islamabad. The project’s salient features
included three generation units with a combined installed generation
capacity of 130mw, a gross head of 1,781 feet, and an estimated annual
power generation of 750 million kilowatt/hours (kwh).
The project’s PC-1, submitted by Wapda to the
Ministry of Water and Power, was discussed at a meeting of the Central
Development Working Party (CDWP) and recommended for approval by Ecnec.
Supplementary topographic and road survey work had been completed by then.
Construction of a project model at the Nandipur Research Station near
Gujranwala had also been completed by then and hydro-flow tests were in
progress.
Wapda’s Hydro-Electric Planning Organisation (Hepo)
was entrusted with the task of planning hydropower projects with a
generation potential of 5mw or more in the country’s riverine system and
on existing canals and barrages on the Indus plains.
Pursuant to specific directives from the government,
Hepo was also involved in identifying and ranking the generation potential
of hydropower schemes, including potential sites for small schemes. Hepo
also conducted surveys and surface and sub-surface geo-technical
investigations for Wapda’s hydropower projects. It also carried out
similar assignments for other government agencies.
After the launch of the then-government’s ambitious
“Vision 2025” water and power development programme in 2001, Hepo’s
responsibilities were further increased as the organisation had been
entrusted with the planning, investigation and development of a large
number of potential hydropower projects on a fast-track basis.
This included preparing feasibility studies for small
hydropower projects on existing canals and barrages in Punjab and Sindh.
The government approved the programme in January 2001. Thereafter, a total
of 591 sites with a combined general potential of 649mw were identified
along various canals and barrages across the country.
The government approved the programme’s PC-II in
October 2001. Data collected by Hepo was reviewed and additional data was
in the process of being collected. Canal and discharge data for all canals
and distributaries with a flow-capacity of 200 cusecs (cubic feet of water
per second) was also in the process of being collected.
Three sites – Machai, Pakpattan and Rohri – were
identified by Hepo as pilot projects. Meanwhile, work on seven other sites
was in progress. Nine sites were allocated to the China National Machinery
and Equipment Corporation for development on a turnkey basis.
International and local manufacturers were consulted for the local
manufacturing of electrical and mechanical equipment for the projects.
Meanwhile, Hepo had also developed standardised design and manufacturing
criteria for the equipment proposed to be locally manufactured.
Funding for low-head hydropower generation projects at
five of the identified sites featured feature in the January 2004 talks
with the KFW delegation. The five sites had a combined generation
potential of about 35mw. While this did not sound like much in the context
of the country’s overall power needs, one of the plus features of the
scheme was the relatively low cost of the individual projects.
Another plus feature of the scheme was that it would
allow hydropower generation plants to be located close to rural demand
centres. This would allow electricity to be supplied to villages and
agricultural tubewells without having to build long-distance transmission
lines to carry power to the demand centres from the generation plants.
The high cost of building long-distance transmission
lines adds to the cost of electricity supplied to consumers. Power
transmitted over long distances also adds to line losses. At the
then-figure of 28 per cent, Wapda’s line losses were amongst the highest
in the world. Building small hydropower generation plants along canals in
the Indus plains near rural demand centres would have helped Wapda to
reduce line losses.
Another hydropower scheme that Hepo was working on in
those days was the Jinnah Hydro Power Project. The project was proposed to
be constructed on the right side of the Jinnah Barrage on the River Indus,
about 5 km downstream of Kalabagh town and 234km from Islamabad. The
project’s salient features included eight power generation units with a
combined capacity of 96mw, a gross head of 16 feet, and an annual
estimated power generation of 688 million-kwh.
The project’s PC-1 was approved by the Ministry of
Water and Power and the Pakistan government. In December 2001, the
government and China’s Dongfong Electric Corporation (Dec) signed a
memorandum of understanding (MoU) for the implementation of the project on
a turnkey basis. A Dec delegation visited the project site in the last
week of December 2001.
In accordance with the terms of the MoU, Dec submitted
its commercial and technical proposal to Wapda in June 2002. Pakistani and
Dec officials were later engaged in talks on financing for the project.
Along with the 1,450mw run-of-the-river Ghazi Barotha
Hydro Power Project on the River Indus 52 km downstream of Tarbela, which
came partly on-stream in mid-2003 with the commissioning of the first of
five 290mw generation units and fully on-stream 18 months later, the
proposed new hydropower projects would have helped to improve the
country’s present highly skewed ratio of 70:30 between thermal and hydel
power plants, enabling Wapda to cut generation costs and, hopefully,
supply cheaper electricity to consumers.
Considering that Pakistan’s electricity tariffs are
now the highest in the world, the need for cheaper electricity has become
all the more pressing in recent years. Hydropower is much cheaper to
produce than thermal power. So the sooner more hydropower plants are built
the better it will be for the country’s economy. That’s why talks with
donor agencies like KFW, the World Bank, the Asian Development Bank and
others to finance hydropower projects are so important.
|